«CAFEC Green Energy» LLP
Objective of the project | "Construction of the wind power plant" Astana EXPO-2017 "with a capacity of 100 MW, for the conversion of wind energy" (First start-up and Second start-up complex for 50 MW) |
---|---|
Capacity | The planned annual amount of electricity upon reaching the design capacity will exceed 130 million kWh / year |
The total cost of the equipment | (1 deal) 5 billion tenge, (2 deal) 17 billion tenge |
Equipment | Kazakhstan, Denmark |
Production | Electrical energy |
Commissioning | First launch complex - 2019, Second launch complex - 2020 |
Influence |
|
Program participant | “Unified Business Support and Development Program “Business Roadmap – 2020” |